Buchtel Stadium Project
Project Updates
July 2026:
Interiors of the Pressbox, Public Restroom and Storage building and the Concession area are beginning to take shape.






June 2026:
- Left: Continued construction at the bottom of the building; New Pressbox at the top of the building with roofing being added to complete the building structure
- Right: The current construction status of the new Public Restroom and Storage Building which is located on the east side of the stadium which will offer women & men's restroom facilities; a family restroom facility with changing table; and storage room for athletic equipment and turf field materials


April 29, 2026:
-
Synergy was working with masons on wall rough in
-
Thompson ran conduit in block with masons
-
Masons started laying block on concessions installed 6 courses on bleacher side and set up scaffolding
-
Tucker delivered another load of CMU
-
Beaver set exterior door frames in restroom building

March 9, 2026:
- Laying foundation block at the press box
- Digging and pouring footers at restroom building
- Removing soil from the site